From Concept to Readiness: SMA’s Role in COASTER's Fast Track

5-minute read
COASTER-hero

Working in close collaboration with Safety and Mission Assurance, engineers at NASA’s Johnson Space Center brought a commercially developed gravity-offload concept from contract option to operational readiness in less than six months. Known as the Counterweight Offload Astronaut-Suited Test and Evaluation Rig (COASTER), the new gravity offload system enables engineers to simulate lunar gravity during astronaut training and testing activities to support future Artemis missions.

What Is a Gravity Offloader?

As NASA prepares for future Artemis missions, astronauts must learn how to operate in lunar gravity while wearing fully pressurized spacesuits that can weigh hundreds of pounds on Earth. Gravity offload systems make that possible.
 
The gravity offloader allows astronauts and test subjects to practice moving, performing tasks and responding to emergencies under reduced-gravity conditions representative of the lunar surface.
 
"For example, if you have an incapacitated crewmember and you’re a mile from the lander, how do you get that person back?" Green said. "That's something you need to practice and understand before you're ever on the lunar surface so you’ll instantly know what to do."
 
These systems support far more than basic mobility training. They help validate spacesuit designs, evaluate astronaut performance, test operational concepts and study human performance in reduced-gravity environments.

"A gravity offloader applies an upward force to someone in a fully pressurized spacesuit," said Houston Green, gravity offload lead engineer for Exploration Extravehicular Activity (xEVA) systems with The Aerospace Corporation at Johnson. "Their overall mass properties remain the same, but we reduce the gravitational effects to simulate what they would experience on the Moon."

While COASTER is an impressive engineering achievement, reaching operational readiness without compromising safety in under six months is an even greater accomplishment. By facilitating collaboration between engineering, safety, quality and operations at the onset, the COASTER project team was able to exercise the contract option in July 2025, and complete the Use Readiness Review in December 2025.

Johnson Space Center already had gravity offload capabilities through the legacy Active Response Gravity Offload System (ARGOS 2B) and the next-generation Axis  AX3S system that is under development.

“We reviewed our current systems and asked, ‘what are we going to do if one if these breaks down?’” Green said. “We have to get the testing done in order for the mission to happen, so protecting the schedule is really a big part of this.”

Aging infrastructure, schedule pressures and growing Artemis testing demands highlighted the need for additional capability. As the team prepared for a new series of elevated suit pressure tests on an accelerated timeline, they faced the challenge of maintaining ongoing operations while expanding capacity. Green and his team sought a solution that would increase testing throughput, enhance operational flexibility and serve as a reliable backup.

Working with commercial partner Atlas Devices, the team evaluated a gravity offload concept that eventually became COASTER. Green said the approach also depended on having a capable and responsive commercial partner. Atlas Devices retained design authority while working closely with NASA to provide the technical evidence, testing and responsiveness needed to support the Government’s acceptance decisions.

“We needed something that could give us another independent capability to absorb appropriate test work, increase the throughput and basically help preserve the more complex active systems for higher priority testing and training,” Green said.

Rather than moving directly to full deployment, the team first tested a prototype with human-in-the-loop evaluations involving flight operations personnel, spacesuit engineers and test subjects. The concept showed promise, leading the team to pursue a full operational system.

While COASTER's engineering accomplishments are notable, Green believes the most important lesson is how the project achieved operational readiness. Instead of developing the system first and then seeking safety approval at the end, the team engaged SMA and quality organizations from the beginning.

Green said the approach began with a simple conversation over some tacos.

"I told Nathan [Vassberg] I would really like to have safety involved up front," Green said.

That early conversation connected Green with Johnson's test safety and quality organizations. From that point forward, safety personnel participated in reviews, testing activities and acceptance planning throughout the project lifecycle.

According to Green, that decision changed everything.

“SMA, quality, engineering, procurement, operations and the vendor were involved from the beginning. We didn't build the system first and then bring safety and quality in at the end."

"We were able to move quickly because SMA, quality, engineering, procurement, operations and the vendor were involved from the beginning," he said. "We didn't build the system first and then bring safety and quality in at the end."

Instead, SMA helped define the acceptance strategy while the system was still being fabricated and delivered. The result was a more focused review process that identified what evidence mattered, what reviews were necessary and where independent NASA oversight would provide the most value.

A key element of the effort was development of a Commercial Item Acceptance Plan (CIAP). The risk-informed CIAP focused on: objective technical evidence, targeted engineering reviews, verification testing, inspections,  and hazard controls, tailoring the acceptance approach to the system’s maturity, intended use, and risk.

For Green, the guiding principle became simple: "Preserve the standard. Challenge the mechanism."

The development team was not looking to reduce safety requirements or quality expectations. Instead, they asked a different question: ‘What evidence does NASA need to confidently determine that a system is safe and suitable for its intended purpose?’

By focusing on risk-informed assurance activities and involving the right organizations early, the team avoided unnecessary delays while maintaining independent oversight and technical rigor.

"Early participation helped identify what evidence, institutional reviews, hazard controls and technical scrutiny were actually necessary," Green said.

After exercising the contract option in July, the team completed its Use Readiness Review in December, achieving operational readiness in less than six months.

Green attributes that schedule success directly to collaboration.

"Commercial speed and engineering rigor don't have to be competing objectives," he said. "When engineering, safety, quality, procurement, operations, management and the vendor are engaged early and understand their roles, rigor can actually enable speed."

The experience has attracted attention beyond the project itself. Other NASA organizations are now evaluating the COASTER project as a model for future commercial acquisitions and acceptance strategies. For SMA professionals, COASTER reinforces a message that safety leaders have advocated for years: safety is most effective when it is integrated from the beginning.

Green went on to challenge the perception that involving SMA early slows progress.

"People want to bring safety in at the end and assume everything will be okay," he said. "That has always seemed counterintuitive to me."

Instead, he views safety organizations as essential partners in mission success.

"For this kind of model to work, SMA and quality cannot be downstream customers of the engineering process," Green said. "They have to be part of defining the assurance strategy from the beginning."

That philosophy not only helped deliver a new capability quickly but also strengthened confidence in the final product.

Today, COASTER is operating within the Space Vehicle Mockup Facility at Johnson and supporting Artemis-related testing activities. The system recently completed dual-suited xEMU validation testing, demonstrating the capability to support two pressurized spacesuits simultaneously in a gravity offload environment.

For Green, however, the lasting legacy of the project may not be the hardware. It is the example it provides for how engineering, SMA and quality organizations can work together to deliver mission-enabling capabilities efficiently while maintaining NASA's high safety standards.

As NASA pursues increasingly ambitious exploration goals, that lesson may prove just as valuable as the technology itself.

"The goal isn't to remove rigor," Green said. "The goal is to understand what really matters, involve the right people early and ensure we're focused on delivering a safe and successful mission."